Debate on French anaerobic digestion had until then rested on little consolidated data. Our sector review is based on a questionnaire sent to 122 sites operating for more than a year, 54 usable responses covering 44 % of that fleet, 44 on-farm and 10 territorial installations, supplemented by 46 interviews across the sector, five site visits and detailed analysis of twelve business plans.

Thirty-two types of deviation were measured, across capital cost overruns, operating cost overruns and revenue shortfalls.

Widespread deviations, heavy profitability loss

94 % of sites had experienced at least one deviation from their business plan. More tellingly, 65 % report profitability below forecast, including 35 % with a severe gap, above 5 points of IRR or gross operating surplus.

No category escapes. Every capacity band is affected at above 89 %, whatever the dominant feedstock. Age offers no protection either: recent sites face as many difficulties as those running for six or seven years. The number of deviations does tend to rise with plant size, and it is the larger sites and those handling mainly external waste that report the greatest impact.

Capital cost overruns are not what hurts most

This is the survey’s most counter-intuitive finding. Capital cost overruns are the most frequent deviation, but their impact on profitability is limited. It is revenue shortfalls, averaging more than 5 points of IRR, and operating cost overruns that weigh heaviest.

Revenue shortfalls stem first from below-plan operation, cited by 53 % of the panel. Plants ran on average 7,272 hours a year, with wide variation: from 5,951 hours for sites of 150 to 250 kWe to 7,701 hours for those between 500 kWe and 1 MWe. Among sites below 1 MWe reporting lower revenue, 100 % cite operating hours as a main cause.

Waste gate fees are the second factor, with price falls of 20 to 90 % and, in several cases, expectations that they will disappear altogether in the short term.

Three causes of degraded operation

  • Digestion process breakdowns and malfunctions: 24 sites, 44 % of the panel. The leading causes are equipment unsuited to the feedstock and design faults. The standard completely mixed process proves fragile against the contaminants found in farmyard manure.
  • Cogeneration breakdowns and shutdowns: 17 sites, 31 % of the panel. Among affected sites below 1 MWe, 53 % identify grid outages as the main cause, with accelerated engine wear as a consequence.
  • Difficulty sourcing complementary feedstock: 16 sites, 29 % of the panel, driven by competition from neighbouring countries and new regional plants.

The absence of local after-sales service amplifies every incident

Maintenance overruns affect 50 % of sites on the digestion process and 38 % on cogeneration, excluding contract fees. Agitators and pumps are the most affected equipment, and these costs were generally not provisioned.

The problem is not the breakage alone but the delay. Without structured local after-sales service, repairs can take several weeks in extreme cases, pushing operators to hold expensive spare parts inventories. Every breakdown therefore becomes an extended shutdown, and so a revenue loss, precisely the item that weighs most on profitability.

To go further, download our full analysis below or contact our experts.

The downloadable PDF of this study is available in French only.